ISO Weeks

Plants plan in weeks, and most use ISO weeks: Monday to Sunday, week 1 being the week with the year's first Thursday. The demo calendar has an iso_week column but no ISO year, and that gap is enough to corrupt every week that straddles a year boundary. In this data that is each week 1; from January 2027 it would be week 53 of 2026 as well.

Where It Breaks

Of the 974 days in dim_date, 5 sit in a different ISO year from their calendar year: Dec 30, 2024, Dec 31, 2024, Dec 29, 2025, Dec 30, 2025, Dec 31, 2025. They are in ISO week 1 of the next year. A matrix with calendar year and iso_week on the rows files them under week 1 of their own calendar year instead, beside a January week they don't belong to.

Units produced in each week-1 bucket, grouped the wrong way (calendar year + ISO week) and the right way (ISO year + ISO week).

BucketWrong: dates in itUnitsRight: dates in itUnitsOff by
2024-W1 Jan 1, 2024 to Jan 7, 2024 and Dec 30, 2024 to Dec 31, 2024 205,804 Jan 1, 2024 to Jan 7, 2024 145,282 +42%
2025-W1 Jan 1, 2025 to Jan 5, 2025 and Dec 29, 2025 to Dec 31, 2025 178,052 Dec 30, 2024 to Jan 5, 2025 148,337 +20%
2026-W1 Jan 1, 2026 to Jan 4, 2026 60,967 Dec 29, 2025 to Jan 4, 2026 151,204 -60%

The wrong grouping makes "week 1" a bucket of 4 to 9 days. A weekly chart then shows a spike or a hole every January, and anyone comparing week 1 with last year's week 1 is comparing different numbers of days.

The Fix

Add an ISO year column and use it with iso_week everywhere a week is the grain. The ISO year is the calendar year of the week's Thursday, which is one line of DAX. Then pick the comparison you mean:

Calculated columns on dim_date:

-- The ISO year is the calendar year of the week's Thursday
ISO Year =
YEAR ( dim_date[date] - WEEKDAY ( dim_date[date], 2 ) + 4 )

-- One value per ISO week, for the axis and as the sort column of a label
ISO Year Week = dim_date[ISO Year] * 100 + dim_date[iso_week]

ISO Week Label =
dim_date[ISO Year] & "-W" & FORMAT ( dim_date[iso_week], "00" )

Measures:

Units Produced = SUM ( fact_production_hourly[units_produced] )

-- Same weekdays a year back: 52 weeks, not one calendar year
Units 52 Weeks Ago =
CALCULATE ( [Units Produced], DATEADD ( dim_date[date], -364, DAY ) )

-- Same ISO week number in the previous ISO year. Blank for week 53
-- when last year had only 52, which is the honest answer.
Units Same ISO Week LY =
VAR Y = SELECTEDVALUE ( dim_date[ISO Year] )
VAR W = SELECTEDVALUE ( dim_date[iso_week] )
RETURN
    IF (
        NOT ISBLANK ( Y ) && NOT ISBLANK ( W ),
        CALCULATE (
            [Units Produced],
            REMOVEFILTERS ( dim_date ),
            dim_date[ISO Year] = Y - 1,
            dim_date[iso_week] = W
        )
    )

Sort ISO Week Label by ISO Year Week, or 2025-W10 sorts before 2025-W2. The site computes ISO weeks independently of the demo calendar and its tests check the two agree on every day, and that every correctly grouped week has seven days.